FAA Names El Dorado and Amarillo in the Ground-Stop Flood and Pauses Juniper Installs

The FAA's 15 November questions page names a new router at El Dorado, Arkansas, and an Amarillo radar site as potential sources of the data flood, and says Juniper installs are paused. The root-cause investigation is still open. DOT and OMB have asked Congress for $50.1 billion.

T
The Flight Brief Editorial Desk

Organizational byline

Updated November 19, 2026

5 min read

News. The Federal Aviation Administration's questions page names two sites in the data flood behind the 13 November nationwide ground stop: a radio site at El Dorado, Arkansas, where L3Harris was installing a new router, and a radar site at Amarillo, Texas. The same page says the broadcasting function was turned off on all the new routers, and that the agency has paused installing Juniper routers. It also says the root-cause investigation is still going. The page does not close either site into a finished cause.

The page is dated Sunday, 15 November 2026. The stop itself, from 3:30 p.m. to 8:15 p.m. ET, is in the ground-stop note.

What the FAA page says

On the cause question, the page says legacy equipment became unstable when data flooded the FAA FTI network at 1,000 connection attempts every 4 to 5 seconds. It says that disrupted aircraft communications and radar feeds.

The initial investigation, the page says, indicates two potential locations for that flooding: the Amarillo radar site and the El Dorado radio site. L3Harris, which the page calls the current network service provider, had been working at El Dorado, including deployment of a new router. When the data inconsistencies happened, L3Harris blocked those two locations and the network stabilized. The broadcasting function was also disabled on all the new routers, the page says, as a precaution.

A later answer names the brand. The FAA says it believes it addressed the initial cause by immediately disabling the functionality of the originating Juniper routers. As a precaution, it says it disabled the same functionality on more than 60 other Juniper routers, and that it has paused installing them. The page gives no date for the pause and no date for installs to start again.

The cause answer still says the FAA and L3Harris continue to investigate the root cause. Naming the sites and disabling the routers is not a published finding of why the equipment behaved as it did.

The page says that, on the evidence it has, there is no indication of a cyberattack or an outside actor. It says the stop was not caused by SMART, which it calls a data aggregator that does not feed the air traffic control system. It says none of the upgraded towers tied to the Working Families Tax Cuts down payment went down. Instability began at 17 of the FAA's 22 air route traffic control centers. That count is in the centers note.

A separate answer says the disruption followed a routine replacement at a remote facility, and that the FAA will reevaluate when that work is done. That sentence does not name El Dorado.

The lab account is CNBC's

CNBC reported on 18 November that engineers had replicated, in a lab in Florida, the situation overwhelming parts of the system. CNBC attributed the replication, and the statement that investigators have yet to determine exactly why two routers failed, to unnamed people speaking about an open investigation. CNBC also reported that investigators said the router began transmitting too much data within eight minutes of installation, and that Transportation Secretary Sean Duffy described a surge of 1,000 connection attempts every four to five seconds. The rate is on the FAA page. The eight-minute figure and the Florida lab are CNBC's.

That account does not finish the cause. CNBC says the replication is progress and that the reason the routers failed is still not determined.

The funding request

On 17 November the Transportation Department said Duffy, FAA Administrator Bryan Bedford and Office of Management and Budget Director Russ Vought asked appropriators for $50.1 billion for a new air traffic control system. The release splits it into $10.1 billion for digital architecture, including more resilient telecommunications, and $10 billion each for airport infrastructure, airport terminals, five consolidated en route centers in place of the current 22, and up to 140 towers.

The release states $50.1 billion. It does not state the previous ask. The Hill, on an 18 November event, said Duffy had raised the request from $30 billion to $50 billion. CNBC reported the same step, from an original $30 billion ask to $50 billion. The Hill's $50 billion and the department's $50.1 billion are not the same number.

The Hill also reported that Bedford called the Arkansas job the 69th installation and said the other 68 had gone well, and that the agency has cited a router in Arkansas and a radar site in Texas as the two likely causes. "Likely causes" is The Hill's phrase. The questions page still says "potential locations," and it still says the root-cause investigation continues.

Sources

The Flight Brief is published by Off The Ground Marketing — aviation marketing for flight schools, charter operators, and MROs.